New Watermain Installation Procedure

(This procedure is for internal staff and engineering consultants only)

For more information on anchor tees for side street connections, see Guidelines on the use of anchor tees for new watermain replacement construction projects.

For situations where an entirely new water service connection is installed and a private water service still has not been installed, the secondary valve shall be installed at the property line.

For more information on anchor tees for water services, see Guidelines on the use of anchor tees for new watermain replacement construction projects.

For more information on anchor tees for fire hydrant leads, see Guidelines on the use of anchor tees for new watermain replacement construction projects .

10 All Water Samples Pass At All Sampling Points

Contractor removes the physical separation backflow preventor. Then install a filler piece or completion piece-must be less than 6.1m-to connect the segment of watermain between the TS&V and first downstream valve located on the newly constructed watermain. Contractor will then install 25 mm copper sampling pipe. Disinfection of the filler piece shall be according TS 7.30.09.07 Installation of Final Connections and Appurtenances. A Toronto Water Certified Operator shall obtain one sample from the filler piece for bacteriological testing with the inspector present on site. Inspector to notify Contract Administrator. If the sample passes, proceed to Step 11.

Not All Water Samples Pass At All Sampling Points

Contractor to re-flush or re-disinfect the new watermain, side street connections, and water services 100 mm and larger in diameter according to TS 7.30.09.03 Re-disinfection .

Upon completion of re-disinfection, proceed back to Step 9.