Document ID ca-on-toronto-ppp-2023-07 Title Pollution Prevention (P2) Program URL https://www.toronto.ca/services-payments/water-environment/water-sewer-related-permits-and-bylaws/water-related-permits/alterations-to-drinking-water-infrastructure/ Jurisdiction /ca/on/toronto Subdomain(s) none Language Status completed Analyzed at 2026-05-12 01:54:15.112141+00:00 Relevance inventory_targeted_fetch

Q Qualitative Requirements (28)

Req ID Category Intent Legal Status Name Subdomain(s) Context Conditions Confidence
#Q001administrativeunknownmandatoryPre-submission Application Reviewdrinking water, wastewaterPrior to submitting an alteration application to the City for review and approval, the application must be reviewed and signed by Engineering and Construction Services or Development Review for compliance with the latest version of: the Ministry of Environment, Conservation and Parks’ (MECP) Design Guidelines for Sewage Works, Stormwater Management Planning and Design Manual, Design Criteria for Sanitary Sewers, Storm Sewers and Forcemains for Alterations Authorized under an Environmental Compliance Approval and Watermain Design Criteria for Future Alterations Authorized Under a Drinking Water Works Permit; the City’s Design Criteria for Sewers and Watermains and Standards for Designing and Constructing City Infrastructure.Prior to submitting an alteration application to the Cityhigh
#Q002administrativeunknownmandatoryDWWP Schedule B Conditionsdrinking waterOnly alterations that meet the conditions and requirements in the DWWP Schedule B qualify for submission of an application to the City.high
#Q003administrativereportingmandatoryWatermain Alteration Application Requirements (>6.1 m)drinking waterAn alteration to a watermain longer than 6.1 m requires a watermain application approved under the DWWP prior to construction and must be prepared in accordance with requirements listed in the City’s Application Checklist for Watermain Works and include: MECP Form 1 - Record of Watermains Authorized as a Future Alteration, MECP Pipe Data Form, City’s Supplement A and/or Supplement B (as applicable), and Other documentation as applicable per the Application ChecklistAlteration to a watermain longer than 6.1 mhigh
#Q004reportingreportingmandatoryWatermain Abandonment or Removal Submissiondrinking waterAbandonment or removal of an existing watermain without replacement, to which no existing water services are connected, is exempt from a completed watermain application. The following documents must be submitted for these works: Completed MECP Form 1 Record of Watermains Authorized as a Future Alteration, Technical memo, including rationale for abandonment or removal, and Letter-size key plan(s) of the abandonment or removalAbandonment or removal of an existing watermain without replacement, to which no existing water services are connectedhigh
#Q005administrativereportingmandatorySchedule C Amendment for Non-Pre-Authorized Alterationsdrinking waterThe following alterations are not pre-authorized and must be submitted directly to MECP for approval through a Schedule C amendment application: Pass under or through a body of surface water, unless trenchless construction methods are used; Have a nominal diameter greater than 1500 mm; Result in the fragmentation of the drinking water system; and Connect to another drinking water system, unless there is written consent from the owner or owner’s delegate of the system being connected to.For alterations that are not pre-authorizedhigh
#Q006administrativeunknownmandatoryCLI ECA Program Requirement for Sewage InfrastructurewastewaterAs of June 2, 2025, all new applications for alterations to sewage infrastructure are required to be reviewed under the CLI ECA Program, subject to new MECP CLI ECA forms and City’s new wastewater service fees, as adopted by City CouncilEffective June 2, 2025high
#Q007administrativereportingmandatoryOpen TOR Applications TransitionwastewaterAs of June 2, 2025, any open applications under the TOR Program will be required to submit the new MECP CLI ECA forms (without additional fee payment).Open applications under the TOR Program as of June 2, 2025high
#Q008administrativeunknownmandatoryCLI ECA Schedule D ConditionswastewaterOnly alterations that meet the conditions and requirements in the CLI ECAs Schedule D of Municipal Sewage Collection and/or Stormwater Management Systems qualify for submission of an application to the City.high
#Q009administrativereportingmandatorySewage Infrastructure Alteration Application RequirementswastewaterAn alteration to sewage infrastructure requires a sewage application approved under the CLI ECA prior to construction and must be prepared in accordance with requirements listed in the City’s Application Checklist for Sewage Works and include: MECP CLI ECA forms, as applicable per alteration type listed in the table below, MECP Pipe Data Form, as applicable, City Supplement A and/or Supplement B (as applicable), Other documentation as applicable per the Application ChecklistAlteration to sewage infrastructurehigh
#Q010reportingreportingmandatorySewage Infrastructure Abandonment SubmissionwastewaterAbandonment or removal of existing sewage infrastructure without replacement, to which no existing sewer services are connected, is exempt from a completed sewage application. The following documents must be submitted for these works: Completed MECP CLI ECA form(s), as applicable per alteration type in the table listed above, Technical memo, including rationale for abandonment or removal, and Letter-size key plan(s) of abandonment or removalAbandonment or removal of existing sewage infrastructure without replacement, to which no existing sewer services are connectedhigh
#Q011administrativereportingmandatorySchedule C Amendment for Non-Pre-Authorized Sewage AlterationswastewaterThe following alterations are not pre-authorized and must be submitted directly to MECP for approval through a Schedule C amendment application: Pass under or through a body of surface water unless trenchless construction methods are used or the local Conservation Authority has authorized an alternative construction method; Have a nominal diameter greater than 3000 mm for a sanitary sewer, 4000 mm for a combined sewer, 6000 mm for a storm sewer, 600 mm for a sanitary forcemain, 600 mm for a combined forcemain, and 900 mm for a storm forcemain; Add new sewage pumping station with capacity greater than 100 L/s; Alter storm sewer/forcemain to be a concrete channel, to convert rural road cross section ditches to curb, gutter and storm sewers that increases stormwater volume and/or peak flow without achieving water quality criteria, to increase storm flow in existing sewer/ditch without achieving water quality criteria unless existing downstream system has sufficient residual transmission and treatment capacity to accommodate the additional stormwater, or to exceed the capacity of downstream pumping station; Connect to another municipal sewage collection system, unless there is written consent from the owner or owner’s delegate of the system being connected to; Create a new sanitary and/or combined discharge point to the natural environment; Result in a new combined sewage storage tank; Establish stormwater management (SWM) facility for regional SWM end-of-pipe flood control, as new outlet discharging directly to the natural environment without treatment and monitoring, to service a drainage area greater than 65 ha or to convert an existing SWM facility to another type of SWM facility; Receive or will receive a Section 16 Order (previously known, as Part II Order) under Environmental Assessment Act s.16; Determined to impact Indigenous treaty rights or asserted right.For sewage alterations that are not pre-authorizedhigh
#Q012administrativereportingmandatoryVerification for Inspection and TestingwastewaterThe designated City case manager is required to complete Part 5 of the previously accepted MECP CLI ECA Forms (i.e., SS1, SW1 and/or CS1) and submit via email to DWWP-ECA@toronto.ca.Post-Construction Submissionhigh
#Q013reportingreportingmandatoryDirector Notifications for Sewage Completion or Ownership ChangewastewaterThe designated City case manager is required to complete Director Notification Form(s) for sewage collection and/or stormwater management system as applicable, as per CLI ECAs Schedules B and /or D Conditions. Submit the required documents by: Emailing MECP at ECA.Submissions@ontario.ca, and Copying the City at CLIECA.DN@toronto.caPost-Construction Submissionhigh
#Q014reportingreportingmandatoryDirector Notifications Submission TimelinewastewaterThe submission is required within 30 days after: 1. Placing into service or completion of any alterations of specific sewage infrastructure facilities (e.g. stormwater management works, pumping stations, combined sewer regulators/tanks). 2. Ownership change/assumption of any alteration works. 3. Ownership change of sewage works approved under individual ECA under the previous Transfer of Review Program, including the following: A request from the owner of individual ECA (such as the developer, transit authority, etc.) to revoke the ECA, and A copy of an agreement or other documentation that demonstrates that the City has assumed ownership of the sewage works and that the ECA should be revoked.Within 30 days after placing into service, completion, or ownership changehigh
#Q015administrativereportingmandatoryAuthorized Signatures on Application Formsdrinking water, wastewaterAll forms must be signed by authorized persons from all parties before submitting an application for alterations to drinking water and sewage infrastructure.Before submitting an applicationhigh
#Q016administrativeunknownrecommendedApplication Submission by Case Managerdrinking water, wastewaterA complete application should be submitted by the designated City case manager responsible for primary review or delivery of the project.high
#Q017administrativeunknownrecommendedFee Payment Payable Todrinking water, wastewaterPayments should be payable to “Treasurer, City of Toronto” and include the payer’s name and mailing address.When paying applicable feeshigh
#Q018administrativeunknownmandatoryEFT or Wire Payment Advicedrinking water, wastewaterFor EFT or wire payment, payment/remittance advice is required, including the caption “ECA/DWWP Works Review Fee” and additional payment details (i.e., project name, location, payment date, reference number).For EFT or wire paymenthigh
#Q019administrativeunknownmandatoryMandatory Pre-Construction Approvaldrinking water, wastewaterProposed alterations to municipal drinking water and sewage infrastructure are subject to approval from the City prior to construction.high
#Q020administrativereportingmandatoryCity Review Timeline Obligationdrinking water, wastewaterComments will be provided to the case manager and copied to the consultant(s) within 10 business days from receipt of the application and each subsequent re-submission.Following the receipt of a complete application packagehigh
#Q021administrativeunknownmandatoryLarge Project Surcharge FeewastewaterAdditional fee for each CLI ECA form when estimated cost of proposed sewage works exceeds $4 million or total pipe length exceeds 1 kmestimated cost of proposed sewage works exceeds $4 million or total pipe length exceeds 1 kmhigh
#Q022prohibitionunknownmandatoryCessation of Transfer of Review ProgramwastewaterThe City no longer accepts new applications under the Transfer of Review (TOR) Program.Effective June 2, 2025high
#Q023administrativereportingmandatoryMECP Form CS1 for Combined Sewage AlterationswastewaterModification, replacement or relocation of: combined sewers, combined forcemains, overflow regulators, combined sewage storage tanks, outfalls [must use] Form CS1 - Record of Future Alteration Authorized for Combined Sewers/Partially Separated Sewers/Combined Sewage Storage Tankshigh
#Q024administrativereportingmandatoryMECP Form SS1 for Separate Sewage AlterationswastewaterAddition, modification, replacement or extension of: sanitary sewers, sanitary forcemains [must use] Form SS1 - Record for Future Alteration Authorized for Separate Sewers/Nominally Separate Sewers/Forcemainshigh
#Q025administrativereportingmandatoryMECP Form SS2 for Sewage Pumping ComponentswastewaterAddition or modification of: sewage pumping stations, in-line/off-line storages [must use] Form SS2 - Record of Future Alteration Authorized for Components of the Municipal Sewage Collection Systemhigh
#Q026administrativereportingmandatoryMECP Form SW1 for Storm Infrastructure Alterationsrecreational waterAddition, modification, replacement or extension of: storm sewers, ditches, culverts, storm forcemains, outfalls [must use] Form SW1 - Record of Future Alteration Authorized for Storm Sewers/Ditches /Culverts/Forcemainshigh
#Q027administrativereportingmandatoryMECP Form SW2 for Stormwater Facilitiesrecreational waterAddition, modification, replacement or extension of: stormwater management facilities, stormwater pumping stations [must use] Form SW2 - Record of Future Alteration Authorized for Stormwater Management Facilitieshigh
#Q028administrativereportingmandatoryMECP Form SW3 for Third Pipe SystemsotherAddition, modification, replacement or extension and operation of: works comprising a municipal Third Pipe Collection System to collect foundation drainage and groundwater [must use] Form SW3 - Record of Future Alteration Authorized for Third Pipe Collection Systemshigh

P Quantitative Requirements (25)

Req ID Category Intent Legal Status Name Subdomain(s) Limit Type Limit Value Context Conditions Confidence
#P001designreportingmandatoryWatermain length requiring approved applicationdrinking waterrequirement> 6.1 mAn alteration to a watermain longer than 6.1 m requires a watermain application approved under the DWWP prior to constructionhigh
#P002designreportingmandatoryShort length watermain modification or replacement exemptiondrinking waterrequirement<= 6.1 mModification or replacement of an existing watermain that is 6.1 m or less in length is exempt from requirements that the design is prepared by a professional engineerhigh
#P003designoperationalmandatoryWatermain nominal diameter limit for pre-authorizationdrinking waterrequirement> 1500 mmAlterations that have a nominal diameter greater than 1500 mm are not pre-authorized and must be submitted directly to MECP for approvalhigh
#P004designoperationalmandatorySanitary sewer nominal diameter limit for pre-authorizationwastewaterrequirement> 3000 mmMust be submitted directly to MECP for approval if nominal diameter greater than 3000 mm for a sanitary sewerhigh
#P005designoperationalmandatoryCombined sewer nominal diameter limit for pre-authorizationwastewaterrequirement> 4000 mmMust be submitted directly to MECP for approval if nominal diameter greater than 4000 mm for a combined sewerhigh
#P006designoperationalmandatoryStorm sewer nominal diameter limit for pre-authorizationwastewaterrequirement> 6000 mmMust be submitted directly to MECP for approval if nominal diameter greater than 6000 mm for a storm sewerhigh
#P007designoperationalmandatorySanitary forcemain nominal diameter limit for pre-authorizationwastewaterrequirement> 600 mmMust be submitted directly to MECP for approval if nominal diameter greater than 600 mm for a sanitary forcemainhigh
#P008designoperationalmandatoryCombined forcemain nominal diameter limit for pre-authorizationwastewaterrequirement> 600 mmMust be submitted directly to MECP for approval if nominal diameter greater than 600 mm for a combined forcemainhigh
#P009designoperationalmandatoryStorm forcemain nominal diameter limit for pre-authorizationwastewaterrequirement> 900 mmMust be submitted directly to MECP for approval if nominal diameter greater than 900 mm for a storm forcemainhigh
#P010designoperationalmandatoryNew sewage pumping station capacity limit for pre-authorizationwastewaterrequirement> 100 L/sAdd new sewage pumping station with capacity greater than 100 L/s must be submitted directly to MECP for approvalhigh
#P011designoperationalmandatorySWM drainage area limit for pre-authorizationwastewaterrequirement> 65 haEstablish stormwater management facility to service a drainage area greater than 65 ha must be submitted directly to MECP for approvalAs new outlet discharging directly to the natural environment without treatment and monitoringhigh
#P012designunknownmandatoryTotal pipe length threshold for additional CLI ECA form feewastewaterrequirement> 1 kmAdditional fee for each CLI ECA form when estimated cost of proposed sewage works exceeds $4 million or total pipe length exceeds 1 kmhigh
#P013operationalreportingmandatoryDry cleaners and commercial laundries P2 Plan submission frequencywastewaterrequirement6 yearsDry cleaners and commercial laundries must submit a P2 Plan every six yearshigh
#P014operationalreportingmandatoryDry cleaners and commercial laundries P2 Plan update frequencywastewaterrequirement3 yearsUpdate on the third year of the six-year cyclehigh
#P015operationalreportingmandatoryHealth care institutions P2 Plan submission frequencywastewaterrequirement6 yearsHealth care institutions must submit a P2 Plan every six yearshigh
#P016operationalreportingmandatoryHealth care institutions P2 Plan update frequencywastewaterrequirement3 yearsUpdate on the third year of the six-year cyclehigh
#P017operationalreportingmandatoryCommercial printers P2 Plan submission frequencywastewaterrequirement6 yearsCommercial printers must submit a P2 Plan every six yearshigh
#P018operationalreportingmandatoryCommercial printers P2 Plan update frequencywastewaterrequirement3 yearsUpdate on the third year of the six-year cyclehigh
#P019operationalreportingmandatoryIndustrial facilities P2 Plan submission frequencywastewaterrequirement6 yearsIndustrial facilities must submit a P2 Plan every six yearshigh
#P020operationalreportingmandatoryIndustrial facilities P2 Plan update frequencywastewaterrequirement3 yearsUpdate on the third year of the six-year cycle using the P2 Plan Update Formhigh
#P021operationalreportingmandatoryNon-sector facilities requested P2 Plan submission frequencywastewaterrequirement6 yearsUpon request from Toronto Water, non-sector businesses must submit a P2 Plan every six yearsAs a result of regular inspection or samplinghigh
#P022operationalreportingmandatoryNon-sector facilities requested P2 Plan update frequencywastewaterrequirement3 yearsUpdate on the third year of the six-year cycle using the P2 Plan Update FormAs a result of regular inspection or samplinghigh
#P023operationalreportingmandatoryAutomotive service facilities one-time declaration requirementwastewaterrequirement1 timeSubmit a one-time Declaration Form confirming compliance with the BMP.high
#P024operationalreportingmandatoryDental facilities one-time P2 Plan requirementwastewaterrequirement1 timeSubmit a one-time P2 Plan using the Dental Facilities P2 Form.Applicable to dental offices that handle amalgamhigh
#P025operationalreportingmandatoryPhotofinishing facilities one-time declaration requirementwastewaterrequirement1 timeSubmit a one-time Declaration Form confirming compliance with the BMP.high

D Definitions (10)

Req ID Category Name Context Confidence
#D001CLI ECAConsolidated Linear Infrastructure Environmental Compliance Approvalhigh
#D002alterationAn alteration refers to additions, modifications, replacements, extensions or retirements to municipal drinking water and sewage infrastructure that is owned by or to be assumed by the City.high
#D003MECPMinistry of Environment, Conservation and Parkshigh
#D004DWWPDrinking Water Works Permithigh
#D005short length watermainan existing watermain that is 6.1 m or less in lengthmedium
#D006TORTransfer of Reviewhigh
#D007SWMstormwater managementhigh
#D008EFTelectronic funds transferhigh
#D009Third Pipe Collection Systemworks comprising a municipal Third Pipe Collection System to collect foundation drainage and groundwaterhigh
#D010Section 16 OrderSection 16 Order (previously known, as Part II Order) under Environmental Assessment Act s.16high